Afghanistan: Earthquake - OCHA-04: 11-Mar-02

OCHA Situation Report No. 4 Afghanistan - Earthquake 11 March 2002

Situation 1. On 3 March, an earthquake measuring 7.2 on the Richter Scale resulted in a landslide in Karyia-e-Zoa settlement in Samanghan province, where two sections of a cliff fell and produced approximately 30,000 m3 of rubble, blocking the river and making it rise at an estimated rate of 3m per day. In addition, the collapse of the cliff interrupted the existing road link between Aybak and Khuram Sarbagh, and the rising water continues to destroy the road, which was not immediately affected by the landslide. About 5 m3 of water per second is flowing into the "reservoir" which is being formed. The rising of water level is significant and it appears possible that up to 70 percent of the village could be inundated as the flood is rapidly approaching the village. National and International Response 2. IOM, UNICEF and WFP have provided emergency relief assistance to 400 families in the affected area, and pre-positioned relief assistance for another 200 families in both Mazar-i-Sharif and Aybak in case of further need. A team of local NGOs has been tasked to monitor the situation and report to UNOCHA on any dramatic changes in the situation that may warrant further emergency relief assistance to any other families that may be displaced over the next few weeks. Such monitoring will be required until the water level is fully stabilised or reduced. 3. UNOCHA is also working with GOAL, the focal provincial coordination organisation for Samanghan province under the Northern Region Afghan coordination structure, to prepare a concept paper and indicative cost for the next phase of rehabilitation. It is estimated that approximately 700 houses should be reconstructed, for which the provision of skilled and unskilled labour, beams, windows, doors and other construction material will be required. 4. On the technical side, the engineering team led by UNOCHA/UN Mine Action Programme and joined by technical staff from ICRC, HALO Trust, GOAL and other NGOs continued visiting and working on site. The technical team has decided to take a two-pronged approach to emergency engineering response. The first included HALO Trust bringing in two loaders and having a technical team working on the spot from 5 March. Within two days the team managed to remove about 120 m3 of rubble and dig a channel through the main blockage on 8 March. This has allowed a water outflow at a rate of less than 5 m3 per second, reducing the water level dramatically, but not completely. The second approach was to use high volume centrifugal pumps for discharging water. UNOCHA facilitated air transportation of two water pumps (on WFP helicopters) provided by ICRC on 6 March that had the capacity to discharge up to 100,000 litres of water per hour. A team of GOAL, SHA, HALO Trust and UNOCHA was dispatched to continue working on the engineering side. The team included a geologist to advise on the rock face that still looked very fragile. ICRC also provided other material required for this task, including hoses, valves and fuel, while IOM pre-positioned additional fuel in Aybak. The effect of using these pumps was rather small due to their limited discharge capacity. The geologist considers the cliff face very fragile and bound to fall, but it has been difficult to determine when this would happen due to the lack of necessary technical equipment. In addition, a four-member team of engineers from the ISAF visited the disaster site on 11 March to assist in assessing the situation and making recommendations to address the problem. 5. In order to eliminate the existing danger of the rising water threatening further inundation of land, approximately half of the blockage (15,000 m3) will have to be removed. There is also a risk that an additional part of the cliff face would fall and impede all rehabilitation work. Agencies on the ground are currently mobilising the following resources to organise a response: i. A geo-technical expert (within the next 2 days); ii. One plant and one construction engineer with survey equipment (within the next 2 days); iii. Two large excavators with approximately 8 to 10 metres reach of wench with spare parts; iv. High capacity (preferably 6-inch) salvage pumps; v. Four steel gas pipes, each 3.5 metre long and about 1 metre in diameter; vi. Concrete culvert pipes (preferably 1 metre in diameter and 1 metre long); vii. Two TV-130 hydraulic bulldozers. 6. OCHA is in close contact with UNOCHA Offices in Afghanistan and will revert with further information, as it becomes available. 7. This situation report, together with further information on ongoing emergencies, is also available on the OCHA Internet Website at http://www.reliefweb.int Telephone: +41-22-91712 34 Fax: +41-22-917 00 23 E-mail: ochagva@un.org In case of emergency only: Tel. +41-22-917 20 10 Desk Officers: Mr. Ivo Freijsen, Mr. Anvar Munavvarov Direct Tel. +41-22-917 1695/1669 Press contact: (GVA) Ms. Elizabeth Byrs, direct Tel. +41-22-917 26 56 (NYC) Ms. Phyllis Lee, direct Tel. +1-212-963 48 32 distributed by - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Center for International Disaster Information Volunteers in Technical Assistance web: www.cidi.org listserv: www.cidi.org/listsub.htm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - comments/suggestions/requests to incident@cidi.org