Pakistan: Earthquake - IRIN: 09-Oct-06
IRIN
PAKISTAN: Focus on earthquake recovery 12 months on
9 October 2006
[This report does not necessarily reflect the views of the United
Nations]
MUZAFFARABAD, 9 October (IRIN) - One year after the worst natural
disaster in Pakistan's 59-year history, which left 75,000 people dead
and another 3.5 million homeless, progress on earthquake recovery has
remained slow and many reconstruction programmes are facing a funding
deficit.
People in the affected areas have begun the slow process of rebuilding
their lives but reconstruction efforts are being held back by a host of
administrative difficulties and a continuing information gap between the
authorities and the survivors, aid workers say.
"Survivors have begun rebuilding their homes, communities and
livelihoods. But, the rebuilding process has, so far, been very patchy,
slow and complex," Farhana Faruqi Stocker, head of international aid
agency Oxfam, said in the Pakistani capital, Islamabad.
"People need to be clearly informed about the financial and technical
support they are entitled to and the guidance on building
earthquake-resistant homes must be easily available and understandable,"
Stocker explained.
Private housing suffered the most extensive damage from the 8 October
earthquake last year, which ripped through parts of Pakistan's North
West Frontier Province (NWFP) and Pakistani-administered Kashmir.
Some 600,000 rural and 30,000 urban housing units were affected across a
30,000 sq km mountainous terrain, covering nine districts and 4,000
villages, according to the revised damage assessment of the Earthquake
Reconstruction and Rehabilitation Authority (ERRA). Initial estimates
put the number of homes to be rebuilt at 400,000.
Under ERRA's housing reconstruction grant, some 422,777 owners have
already received money - a quarter of whom have started rebuilding,
according to ERRA.
Building Back by 2009
On Thursday, speaking at ERRA's first annual review conference,
Pakistani President Gen Pervez Musharraf promised that 80 percent of the
reconstruction work in quake-hit areas would be completed by 2009, with
housing units finished by December 2008.
He added that the addition of 200,000 homes, following a revised
assessment, has increased the overall cost of reconstruction.
"The cost of US $3.6 billion calculated earlier for the reconstruction
phase has now increased to $4.4 billion, creating a shortfall of $800
million," Musharraf said.
He appealed to the international community and philanthropists to bridge
the funding gap.
Funding gaps in Early Recovery Plan
The lack of funds is also hampering efforts to get sectors such as
health and education up and running again.
In May, the United Nations and ERRA launched an Early Recovery Plan
(ERP) to bridge the gap from relief to reconstruction in the country's
quake-affect north. The total cost of the plan was revised from an
initial $190 million to $255 million.
"As of the end of August, in total, some $161 million had been
mobilised, leaving a funding gap of $94 million," Shoko Noda, a recovery
coordination advisor at the UN Integrated Office of the Resident
Coordinator (UNORC), said in Islamabad.
The ERP, covering a 12-month period from May 2006 to April 2007, charted
concrete proposals in eight sectors, including education, health, water
and sanitation, housing, needs of vulnerable groups, disaster risk
reduction and coordination.
However, many of the sectors have been facing a serious funding crisis.
The health sector has received less than 50 percent of the total $40
million needed to fund its programmes.
"A serious crisis for health of vulnerable people could occur if the
coming winter were to be severe - as some predict it to be," Noda said.
The other least-funded sectors include water and sanitation, housing and
support to vulnerable people.
The annual review report of ERRA, released on Thursday, noted: "The
pledges made in the donors' conference in November 2005 did not
materialise through the Government of Pakistan as envisaged earlier;
rather funding was being channelled directly through implementing NGOs
working in various sectors with communities on the ground."
Missing quality education
While some progress is being made in the provision of the basic needs of
shelter, food and drinking water and rehabilitation of infrastructure,
education experts feel the education sector is missing out.
More than a million schoolchildren were affected by the quake and around
8,000 schools were destroyed or damaged across the affected region.
While thousands of children spent the last year without proper education
in tent schools, education experts estimate they will have to face many
more years without proper classrooms.
Saima Anwer, education director at the Pakistani branch of UK-based
charity Save the Children said: "It will take five to seven years to
rebuild the education system, meaning some children will never get to
attend a real primary school."
"So far bureaucracy, a lack of commitment and insufficient funding for
the education sector has meant that the permanent reconstruction of
schools has been extremely slow and in some places non-existent. School
enrolment rates have also plummeted," Save the Children-UK said in a
statement.
"Despite the problems they face, children and teachers walk for hours
through difficult terrain every morning to get to school. But inadequate
shelter, lack of water supplies and sanitation facilities, shortage of
teachers and learning material - all provided for a poor learning
environment," Anwer said.
"But, even after an emergency, every child has the right to a quality
education. We think they deserve the same enthusiasm from the government
to give them back a safe and conducive learning environment by stepping
up the pace of rebuilding," she added.
Nevertheless, reconstruction and recovery has never been easy.
"When we look at Japan, which is the world's 2nd largest economy, it
took five years to rebuild 140,000 homes after the 1995 quake in Kobe.
Obviously, the Pakistani government does not have that wealth, technical
expertise, institutional framework and experience to deliver faster than
Japan," Oxfam's Stocker said.
IRIN-Asia
Tel: +90 312 454 1177
Fax: +90 312 495 4166
Email: IrinAsia@IRINnews.org
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Appropriate Donations for International Disaster/Humanitarian Needs
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Center for International web: www.cidi.org
Disaster Information listserv: www.cidi.org/listsub.htm
guidelines: www.cidi.org/donate.htm
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
South Asia Earthquake www.cidi.org/incident/sasia-05j